The City of Circleville announced Thursday, March 26th the estimated cost for this year’s street program will cost a near estimated $1,361,000 and includes slurry sealing, paving, crack sealing, spot repairs and miscellaneous work. The total estimated cost is $1,360,928
The following is a complete of the work to be conducted and the associated cost estimates:
Slurry Seal: $165,691
Barnes (Pickaway St. to Clinton St.)
Goodchild Service Rd. (S. Corp. to N. Corp.)
Half Ave. (Clinton St. to Renick Ave.)
Nicholas Dr. (Lancaster Pike to North Ridge Rd.)
Pickaway St. (High St. to Linden Dr.)
Pickaway St. (Sharon Rd. to Northridge Rd.)
Scioto St. (South End to Harrison Ave.)
Washington St. (Walnut St. to Huston St. / RR)
Paving: $1,135,431
Brookhaven Pl. (Clark Dr. to North End)
Court St. (Wilson Ave. to North Corp.)
Eastmoor Ave. (Mound St. to Main St.)
Folsom Ave. (Park Pl. to Pickaway St.)
Franklin St. (Mingo St. to End at SR 56 - Including Connector)
Huston St. (US 23 to Court St.)
Kingston Pike (South Corp. to Main St.)
Lawnwood Dr. (Ridgedale Dr. to Brookhaven Pl.)
Morris Rd. (Court St. to East End)
Northfield Dr. (West end to North End)
Ohio St. ("GE drive" to Kingston Pike)
Park Pl. (Court St. to Folsom Ave.)
Plaza Dr. (Nicholas Dr. to Nicholas Dr.)
Ridgedale Dr. (Clark Dr. to Lawnwood Dr.)
Sherwood Dr. (Cul-de-sac to Nicholas Dr.)
Springhollow Rd. (South End to Clark Dr.)
Woodland Dr. (Folsom Ave. to Cul-de-sac)
Alternate paving would take place along South Court St. if the City has extra funds or cannot do a planned street.
Crack Seal: $9,806
Clifton Dr. (Northridge Rd. to North End)
McCormick Ave. (Clifton Dr. to East End)
Wilson Ave. (Court St. to Atwater Ave.)
Spot Repairs: $50,000
List not included
Miscellaneous work includes Paint Stripping, ADA Curb & Sidewalks, Signs, Signals
Grant Projects:
Cedar Hts. Rd. (Mulberry Rd. to Edgewood Dr.) - OPWC
Turner Dr. (South End to Town St.) - CDBG
Grant Applications:
Cedar Hts. (Mulberry Rd. to Atwater Ave.) - OPWC
Walnut St. (Washington St. to Clinton St.) - CDBG