Chillicothe's Street and Alley Program will continue this week with new paving operations set to begin Wednesday.
-
Work to begin Wednesday, June 12th includes areas in the city's west and south ends.
-
According to a release from the Chillicothe Engineering Department, milling and paving work will begin in the following areas:
- Rose Lane from Fifth Street to Highland Avenue
- Grand Avenue from Belleview Avenue to Fifth Street
- Parsons Avenue from Scothorn Lane to Pohlman Road
- Brookside Road from Belleview Avenue to the end of Brookside
- Mechanic Street from 7th Street to 8th Street
Milling of these areas will begin on Wednesday with paving set to follow on Thursday.
-